SENT ON BEHALF OF SGN:- GAS NETWORK UPGRADE - BOXLEY ROAD, MAIDSTONE
24/04/2025
Please see update below and on our website about our ongoing work to upgrade the gas network in Penenden Heath.
https://www.sgn.co.uk/our-gas-works/major-planned-projects/maidstone-sandling-lane
Update - Tuesday 22 April
We'd
like to thank everyone affected by this essential project for your continuing
patience and support. Our work to upgrade the gas network in the Penenden Heath
area is progressing well. Here's the latest update.
Sandling Lane
Our network upgrades are now completed on Sandling Lane.
Boxley
Road - Phase one
We are currently working along Boxley Road with a road closure in place. We’re
working from the junction of Neville Close down to the roundabout junction with
Sandling Lane and Penenden Heath Road. Once we’ve passed the roundabout,
traffic will once again be able to access Boxley Road going towards Boxley from
Sandling Lane and Penenden Heath Road.
Our engineers have identified some additional pipework which requires further
investigation. We now expect to be able to reopen Boxley Road on the north side
of the Sandling Lane / Penenden Heath Road roundabout from Tuesday 29 April.
Boxley Road will then be closed around our work on the south side of the
roundabout while we complete phase two of our work.
Boxley
Road - Phase two
We’ll continue upgrading our pipes along Boxley road from the Sandling
Lane/Penenden Heath Road roundabout to the junction with Rock Road. A road
closure will be in place around our work as we move along the road. During this
phase, access along Boxley Road going towards Maidstone will be maintained via
a signed diversion route.
Penenden
Heath Road
From 21 July, we’ll be working from the junction with Boxley Road to the
junction with Sittingbourne Road. All going well, this phase will end on
approximately Monday 1 September.